A record's page, in stages

For
a controller working on one planned disruption
Status
current
Covers
a planned disruption's own page — the bar across the top (← Register, the status bar, + Log contact, Save, ⋯, and the
Also here
line), the stage sidebar, ← Previous / Next →, the
Next
line, Not ready, and the question asked when somebody else has the record open (View only, Open it anyway, Back to the register)
Last checked against the app
e6fb893 (2026-11-23) — re-read against the code on 2026-11-23, not against a running app; the passages on closure types written from the code at 58f52358 plus the closure-types changes to the record page (2026-11-19), and not yet read against a running app; the passages on who else is here written from the code at a5344896 plus its working tree (2026-11-20), with no server to try them against — to be read on staging

Opening a record in Kinetic Melbourne OCC — the tool built for Kinetic Melbourne's Operational Control Centre — shows one stage of the job at a time, rather than everything about the record in one long scroll. This page is how that page is laid out, where it opens, and what its marks mean. Every other page in this chapter describes one stage.

What you are looking at

The bar across the top stays put whichever stage you are on. It holds:

  • ← Register — back to the list, with this record still selected;
  • the record's reference and title;
  • the status bar — where the record stands in the job, and the buttons that move it on. It has a page of its own;
  • + Log contact — records an email, call or meeting in the contact log from wherever you are (see the Record file);
  • Save — saves everything on the record that can be saved, wherever it is (see The Save button below);
  • ⋯ — Close this record, Download backup file (JSON) and History;
  • Also here: — who else has this record open, on a line of its own under the rest. It is only there when somebody is (see When somebody else has it open below).

On a laptop or a desk screen the bar is two rows: the record, Save and ⋯ on the first, the status bar with + Log contact on the second. On a very wide screen it is one row. When the status bar asks you something, the question opens in a panel just below the bar, over the page — the bar itself never grows.

The stages are a bar down the left of the page: Describe, Who's affected, Plan diversions, Notify & issue, numbered 1 to 4, and the Record file set apart under them. It stays in view as you scroll. Each stage is a button with one word under its name:

Word Means
Done (green, with ✓ in place of the number) everything that stage needs is in place
Current the stage you are on, not finished yet
Next the first stage that still has work to do, when you are somewhere else — the one to go to
To do a later stage with work still to do
Not ready it still opens — see Not ready is advice, not a lock
Not needed the record's closures need nothing in that stage — no road closure, no diversion to plan; only lane closures, no notice — see The stages follow the closures

The stage you are on has an outline round it, and keeps its ✓ if it is finished. Point at a stage to read where it stands — 1 closure drawn · 2 periods, Assessed · routes to plan, 1 to draw · 1 of 2 drawn, Not issued yet. On a narrow window the bar becomes a row across the top of the page instead.

Under the bar, on the left, is the record itself: its title, a line giving its type and who is handling it — Roadworks · Handled by and their name — and its description, cut to two lines with more to read the rest. Then the stage you are on:

  • ← Previous and Next → at its top-left and top-right, named for the stage they go to — ← Describe, Plan diversions → — and again at the foot of the stage;
  • its title, with its number;
  • one line saying what the stage is for — twelve words or fewer;
  • one Next: line, saying the next thing to do here, with the button that does it — Next: draw Demo St bridge Draw the closure. It disappears when there is nothing left to do on that stage;
  • the stage's own sections.

On the right, one map stays put. It shows what the section you are reading is about — the closures on Describe, the routes on Who's affected, a group's routes when you point at its card.

The five stages

Stage Its line on screen Holds Counts as done when
① Describe Record what the TMC sent: the dates and the closed roads. The periods, the closures, and one line naming the TMC At least one closure is drawn on the map
② Who's affected See which routes, stops and other disruptions the closures touch. Routes affected, Stops affected and Analysis (which ends with Clashes with other disruptions) Every drawn closure is assessed and up to date
③ Plan diversions Draw a detour for each group of routes, and save it. Diversion groups, and the door into each group's planner Every group has a detour drawn and every route in it is on its detour — a saved detour is in use, so there is nothing to approve — or there is nothing to plan; and in either case no closure's assessment is out of date
④ Notify & issue Check the notice, then issue it to the depots. Ready to issue?, The notice, and Issue A version of the notice has been issued
Record file Contact details, correspondence, history and the backup file. Traffic management company, Contact log, History and Backup file Never — it is reference, not a step

Where a record opens

A record opens on the first stage that still has work to do. A new record opens on ① Describe; one whose closures are drawn opens on ② Who's affected; one that is ready for its notice opens on ④ Notify & issue, and so does one that is finished.

A record never opens on a stage that is Not needed. A record of stop closures, once they are placed and assessed, opens on ④ Notify & issue; one of lane closures only opens on ② Who's affected, where its Confirm… is. See The stages follow the closures.

A closure that is not assessed, or whose assessment is out of date, brings a record back to ② — whatever its status. A record at Diversions planned whose closure was moved afterwards opens on ② Who's affected, with Next: recompute Demo St bridge — it is out of date, until it is recomputed. Its register row says Next: check who's affected.

The choice is made once, when you open the record, and it never moves you afterwards. When it depends on something that arrives a moment after the page — the diversion groups, or whether the assessments are up to date — the stage area reads Loading… until it does, rather than guessing and then jumping you somewhere else.

A reload after you save something keeps you on the stage you were on. Leaving the record and coming back is a new opening, and the rule above chooses again.

Not ready is advice, not a lock

A stage that is not ready still opens when you press it, and still shows everything in it. Its Next: line is replaced by the reason, and a button to where the fix is:

Stage Not ready: Button
② Who's affected Draw a closure first — an undrawn one cannot be placed against any route Go to the closures
② Who's affected Choose the closed stop first — the routes are found from the stops it names, when every closure is a stop closure with no stop — which happens only to one made elsewhere; delete it and add a stop closure Go to the closures
③ Plan diversions Assess a closure first — the groups are built from what it finds Go to Who's affected
③ Plan diversions No route goes forward — tick one under Who's affected Go to Who's affected

This matters because a record can already hold work in a stage that has since become not ready — groups drawn, then a closure moved. The mark never puts that work out of your reach.

Describe, Notify & issue and the Record file are never marked not ready. The notice can be read at any time, and issuing it keeps its own list of what is still missing.

The Next: line

Every Next: line is worked out from the record as it stands, and names one action:

Stage What it can say
① Describe Next: add the first closure — a closed stop, lane or road Add a closure · Next: draw Demo St bridge Draw the closure · Next: see which routes and stops it affects Assess, once it is drawn. Stop closures are assessed for you straight after they are added; the line offers Assess for one that was not. A stop closure with no stop says Next: Main Rd stop names no stop — delete it and add a stop closure Go to the closures
② Who's affected Next: assess 2 closures Assess (one press assesses both) · Next: recompute Demo St bridge — it is out of date Recompute · on a disruption with no road closure, once every closure is assessed, Next: confirm the dates and details Confirm…
③ Plan diversions Next: group the routes Group the routes · Next: draw 2 detours with a button naming the first group as its card does (Draw the south-eastbound detour, or Draw South-eastbound · 703, 704 when two groups go that way) · Next: draw the westbound detour Draw the westbound detour, when the one left to draw is the second direction of a both-ways card · Next: recompute Demo St bridge first — its assessment is out of date Go to Who's affected, while a closure's assessment is out of date · Next: the routes going forward changed since grouping Regroup — keeps your changes, before any detour is drawn, when routes were ticked or unticked after grouping · Next: mark the diversions planned Mark diversions planned…
④ Notify & issue While Ready to issue? has something unticked, the first of those with its fix — Next: draw the westbound detour, Next: the notice has no description Write it, Next: mark the diversions planned Mark diversions planned… (on a record of stop closures, Next: confirm the dates and details Confirm…), or on a record of stop closures Next: no route goes forward from the stop closures yet… Go to Who's affected. Once everything is ticked, Next: issue the notice Go to Issuing

A button ending in … only offers the move. Mark diversions planned… — the only status a Next: line offers, called Confirm… on a disruption with no road closure — opens the status bar's own confirmation, in a panel just below the bar at the top, with a box for a note. A new record is already Assessing, so nothing offers that, and going back is a choice you make on the status bar. The status changes when you press that confirmation's own button, and not before. Finishing a stage never changes a status by itself, and nothing ever offers Notice issued — only issuing the notice sets that. The status bar says why.

The stages follow the closures

Every closure has a type — Stop closure, Lane closure (buses allowed) or Road closure (see ① Describe) — and what the record needs follows from the mix:

The closures ③ Plan diversions ④ Notify & issue The steps of its status
Any Road closure among them, or any closure with Type not set needed needed Assessing, Diversions planned, Notice issued, In force
Stop closures only, or stop and lane closures Not needed needed — a short notice listing the closed stops Assessing, Confirmed, Notice issued, In force
Lane closures only Not needed Not needed Assessing, Confirmed, In force

A stage that is Not needed:

  • says so in the bar on the left. It is not marked not ready, it is never green, and the record never opens on it;
  • shows one line instead of its sections — Not needed: A diversion is planned only for a Road closure, and this disruption has none. on ③, Not needed: A lane closure is not put on a notice — buses still get through. on ④ — and one button, Go to the closures, which takes you to ① Describe. That is where a road closure is added, or a lane closure is changed to one.

Once every closure is assessed, a disruption with no road closure offers Next: confirm the dates and details Confirm… on ② Who's affected, which opens the status bar's confirmation. The status that follows reads Confirmed rather than Diversions planned — see the status bar.

A disruption of stop closures then has a notice to issue. ④ Notify & issue is an ordinary stage on it, and it does not wait for anything on ③, which has nothing in it. It is where such a record opens once its stop closures are assessed, and while its status is still Assessing its Next: line is the same Confirm…. The notice is short — see ④ Notify & issue.

One road closure is enough to need every stage. A record with a stop closure and a road closure keeps all four stages as before.

Changing a type

You change what a disruption needs by changing a closure's type on ① Describe and saving it — a lane closure to a road closure, or back — by adding a closure, or by removing one. Either way it is an ordinary save, and nothing is deleted: detours drawn while buses diverted are kept, and so is every notice issued.

The app asks first when the save would leave the record with no Road closure — or, on a record that already had none, with only lane closures — and one of the record's detours is in use, or a notice has been issued. The question starts with what the save leaves, then lists, one line each:

  • each detour that would go back to not in use — drivers stop being given it;
  • each detour shared with another disruption that still needs a diversion, which is left as it is for that disruption;
  • the notice that would be marked out of date, who was given it, and what to do about it — issue one, listing the closed stops, to replace it when stop closures are left; tell the people who were given it that buses are no longer diverted when only lane closures are left; and tell the people who were given it that the stop is open again when it was the last stop closure that went.

Press OK to save, or Cancel to change nothing: the form stays open as you left it. With nothing in use and no notice issued, the save just happens.

A detour put into force by hand on the Diversions tab stops the change. Drivers are following it, so the save is refused, and the message says to stand it down on its own record first.

After the save, the message says what changed — for example Closure saved. No Road closure is left, so buses are no longer diverted. DIV-2026-0031 is not in use now — kept, not deleted. Notice version 2 is now out of date — issue a new notice, listing the closed stops, to replace it. The History in the Record file shows the same save among the key events — Buses no longer diverted — DIV-2026-0031 not in use; notice version 2 out of date, or No notice needed — notice version 1 out of date when only lane closures were left.

What the record then shows:

  • on ③ Plan diversions, under its Not needed line, the old detours folded away under one line — 2 detours from when buses diverted. Open it to see each one, its group, and whether it is in use (one shared with a disruption that still needs a diversion stays in use); each links to its record on the Diversions tab;
  • near the top of the record, and again at the head of ④ Notify & issue, a line saying the notice is out of date. On a record that still needs a notice it says no notice has replaced it yet and that Issuing a new notice replaces it. On a record of lane closures only, which has no notice to issue, it says who was given it — tell them buses run as usual. The register's row carries notice out of date too. Telling them is yours to do — the app records who was given it, and does not contact anyone.

Going back the other way never asks. Making a closure a Road closure again brings the stages back. A Confirmed record with no detour in use goes back to Assessing in the same save, and the message says so. No detour is put back in use by itself: open its group in the planner and save it, so you check the path still fits the closure as it is now.

Moving between stages

Press a stage in the bar on the left, press ← Previous or Next → at the top or the foot of the stage, or use [ and ] — the buttons and the keys go to the same places. The Record file comes after Notify & issue. Next → only moves you; the Next: line under the stage's title is the one that says what to do. A link from somewhere else in the app — an entry in Recent activity, say — opens the record at the stage that holds what it names.

Leaving a stage with unsaved work asks first, in the words of what would be lost — "Discard a closure? It cannot be recovered." Cancel keeps you where you are with your typing intact. OK really does discard it: the stage you leave is taken off the screen, not hidden, and that includes a form half filled in, a drawing tool you had started on the map, and ticks under Who's affected you had not saved.

A closure's form counts as unsaved when anything in it differs from what it opened with — the notes or the stops typed into a new closure count even before it has a name. A closure you opened with Edit only to read, and did not change, is not asked about.

Two things you type are kept while the record stays open: the changes to what the notice says, and the list of who receives it under Issue. Moving between stages does not ask about them, because nothing is lost — they are there when you come back. The question comes when you open another record, which is when they would go.

While a group's detour is being drawn, the planner takes over the left side, and the stage bar becomes a trail — Plan diversions, with the group's name under it (on a narrow window, beside it after a ›). Pressing Plan diversions there brings you back to the groups. See Drawing a group's detour.

The Save button

Save, in the bar at the top, is there on every stage and while a group's detour is being drawn. It reads All saved when nothing on the record is waiting to be saved, and Save as soon as something is.

It does not save anything new by itself: it presses the page's own save buttons for you — the closure you are drawing, a closure's moved shape, your ticks under Who's affected, a closure, contact-log or traffic management company form you have filled in, the changes to what the notice says (even from another stage), and — while the group planner is open on its Review and save step — the planner's own Save and put into use. Then a small panel under it says how it went: Saved, or a list of what it could not save, each with why and a Go there button.

Saving a detour puts it into use, whichever button you press, so when the Save presses the group planner's button the panel says so by name — Saved — the detour South-eastbound · 703, 704 is now in use. Drivers see it when the notice is issued. If the planner's checklist is not done yet, the Save leaves the detour alone and lists it: save it on the Review and save step.

It never does these for you, because each one is a decision of its own, and it lists them instead:

  • a note typed for a status change — saving it moves the status;
  • a reason typed for retiring a detour — saving it retires the detour;
  • an edited copy of the notice you have chosen but not attached;
  • the list of who receives the notice — it is never stored; it is used when you issue.

After a save, the page stays where you were. Every save reloads the record. While it does, the page cannot be clicked or typed in — so nothing you type is lost to the reload — and if the reload takes more than a moment the page fades a little. Then the new version takes its place without the page jumping back to the top. A form's own save button says Saving… (or Moving…, Adding…) while its save is going through, and cannot be pressed a second time.

Go there marks where it took you. The part of the page a Go there button brings into view keeps a grey outline until your next click or key press, so you can see what you were sent to.

Sometimes it saves nothing, on purpose. Every save reloads the record, and a reload clears anything on the page that is not saved yet. So if a drawing on the map cannot be saved as it stands — a line with one point, say — or a form is missing something it needs, or there are two unsaved forms open at once, the button saves nothing at all and tells you why, rather than lose that work. Save or cancel those with their own buttons, then press Save again. The same goes if the drawing or form it tries first is refused — a closure with One direction chosen and no direction picked, say: it stops there, keeps your work on the page, and lists the rest as not saved yet.

When somebody else has it open

Opening a record tells the app you have it open, and the app tells everybody else who has it open too — as it happens, without anyone reloading.

The Also here: line. A line in the bar at the top names everybody else who has this record open, and what they are doing. People are named by the name they have set for themselves in their account, and by their sign-in name where they have not set one:

  • alex · editing — they have changes on their page that they have not saved;
  • sam · viewing — they have it open and nothing unsaved;
  • You, in another tab — you have it open in another tab or window as well. That counts: two tabs of yours saving the same record can undo each other just as two people can;
  • alex (2 tabs) — one person with the record open twice.

It changes as people come and go: within a second or two when somebody opens or closes the record, and the moment somebody starts typing (viewing becomes editing) or saves (editing goes back to viewing). Somebody who opens the record after you did is added to the line, and a line under it says so — jo has joined since you opened this. The line takes no room at all when nobody else has the record open.

The question before you edit. If somebody already has the record open when you open it, and you are allowed to change it, a question comes up before you can — for example:

alex is editing this disruption. sam is viewing it.

Two people saving the same disruption can undo each other's changes.

The people editing are named first. You have three answers:

Answer What happens
View only The record opens as a Viewer sees it — everything readable, nothing you can change, no Save (see Reading a record you may not change). A drawing tool or a shape you had started on the map, and an open period, are put away. The Also here: line says View only, with Switch to editing if you change your mind. It lasts until you leave the record
Open it anyway The record opens as normal. Use it when you have agreed with the others who is making the change
Back to the register You go back to the list, and nothing on the record is touched. Escape does the same

The question is asked once, when you open the record. Somebody who arrives afterwards does not bring it back — they appear on the Also here: line instead. Going to another tab of the app and coming back is not opening the record again, so it does not ask again either — unless you left the question unanswered, in which case it is asked again when you come back. Going back to the register and opening the record again asks again.

A question never opens on top of work you have started. It comes up only in the first few seconds after you open the record, and only while nothing on the page is waiting to be saved. If the app finds out later than that (a slow connection, say), or you have already started typing, the Also here: line says it instead — alex already had this disruption open when you opened it. — with View only beside it, which does exactly what the question's View only does.

If you have typed something and then choose View only or Back to the register, you are asked first whether to throw it away. Answer Cancel and you stay exactly where you were: your typing is kept, and the question is still there to answer.

When the line cannot keep up. If the connection drops, the line says Not up to date — trying to reconnect. under the names, which may then be old, until it is back. If the app has stopped finding out altogether — you were signed out, for example — it says No longer updating — reload the page to see who else has it open. An empty line never means that nobody is there when the app does not know.

Reading a record you may not change

Signed in as a Viewer, having chosen View only, or reading a record that is cancelled or withdrawn, you get the same stages and the same stage bar — with nothing marked not ready, no Next: lines, no + Log contact and no Save. A closed record also carries a line under its title: Closed (Cancelled) — nothing more can be edited, logged or moved.

What the marks do not mean

✓ on Describe does not mean the dates are in. It means at least one closure is drawn — or is a stop closure, which is placed by its stop. A record with two closures and one drawn shows ✓ and 1 of 2 drawn; where a stop closure is among them it says placed instead of drawn. A record with no periods says no dates yet in the same line. Read the line, not only the tick.

Not needed is not the same as done. It means the record's closures need nothing there — not that a detour has been drawn or a notice issued. If that changes, Go to the closures takes you to where a road closure is added, and the stages come back.

✓ on Who's affected means every drawn closure has an assessment that is up to date. A closure moved afterwards takes the tick away until it is recomputed. Closures that are not drawn are not counted, because they cannot be assessed — ①'s line says how many of those there are.

✓ on Plan diversions is worked out from the groups: every group drawn, every route in it on its detour, and no warning that the routes going forward have changed since the groups were made. When you tick or untick a route under Who's affected after grouping, the tick goes and the stage asks you to Regroup — see ③ Plan diversions. A record grouped before that warning existed cannot tell, until it is regrouped.

No ✓ on Plan diversions while an assessment is out of date. Its answer — the detours drawn, or Nothing to plan — comes from the assessment, so when the dates change or a closure moves and Who's affected says out of date, Plan diversions loses its tick too and reads Assessment out of date · … until the closure is recomputed.

Nothing to plan is finished, not broken. On most closures, some of the routes found are another operator's — not Kinetic's or Dysons' — and they are left out of the planning from the start. When that leaves none of ours (the stage then reads Assessed · none of ours, and pointing at it names Kinetic and Dysons), Plan diversions says Nothing to plan and counts as done. When routes of ours were found and every one was unticked, it says Nothing goes forward and is marked not ready, because that is worth a second look.

The stage bar never says how many routes. The one count it could use adds a route twice when two closures hit it, so it says only whether routes go forward. The list itself is on Who's affected.

Also here: tells you; it does not stop you. Nothing stops two people saving the same record. The line and the question tell you somebody else is there so that you can agree who makes the change; if you both save, the later save can undo the earlier one.

editing means unsaved changes on their page, not that they are about to save, and not which part of the record they are changing. viewing does not mean they will not start.

Names are account names — the name the person signs in with. Where the app has no sign-in, nobody can be named, and the line says Open in another browser, or Open in 2 other browsers, instead.

Nobody on the line is not proof nobody is there. Somebody whose connection has dropped can take up to about a minute to disappear from the line, and on a connection that cannot be held open the line catches up about every fifteen seconds rather than at once.

The stage you were on is not saved anywhere. Not in a setting, and not in a link you copy. Whoever opens the record next lands where the rule above says.

When it looks wrong

The stage area says Loading… and stays that way. The app is still waiting for the diversion groups, the assessments or the issued notices to arrive. Reload the page. If a read fails outright, the page stops waiting and opens on the stage that says what failed.

You pressed Mark diversions planned… and the status did not change. The button opens a confirmation in a panel just below the bar at the top of the page. Press Move to Diversions planned there.

There is no Next: line. There is nothing left to do on that stage, or you are reading as a Viewer, or the record is closed — or what the line would offer is already open in front of you: the closure form, or the drawing tool.

Save said Nothing saved. Something on the page would have been lost if it had saved — the list says what. A drawing on the map that is not finished, or a form with a box left empty, is the usual one. Finish it or cancel it, then press Save again.

Save still says Save after I saved everything I can see. Something is waiting on another stage — most often the changes to what the notice says on ④ Notify & issue. Press Save: its list says what and where.

The question did not come up, but the Also here: line names somebody. They opened the record after you did — the question is only asked when you open it. Or you are signed in as a Viewer, who is never asked: there is nothing for a Viewer to change.

There is no Also here: line at all, even with a colleague in the record. This deployment does not offer it. If the app had been showing it and stopped, the line says so in words rather than going blank — see When the line cannot keep up above.

The keys [ and ] do nothing. They work on a record's page when the group planner is not open, and not while you are typing in a box.